Planning a Pharmacy Buildout in Houston

Published · BPC Development LLC

Independent pharmacies, clinic pharmacies, specialty pharmacies and compounding pharmacies all open in Houston strip centers, medical office buildings and freestanding buildings. From the parking lot, a pharmacy can look like any other retail suite. Behind the counter, it is a controlled space with security, storage, workflow and sometimes clean-room requirements that a typical retail buildout never has to think about.

Owners and landlords who plan a pharmacy like an ordinary retail space often run into problems late in the project: the drop ceiling doesn't support the security design, the compounding room can't hold the right air pressure, the plumbing is in the wrong place, or the board inspection turns up layout issues that should have been caught on paper. This guide walks through what to plan before construction begins.

This page is general information, not legal, pharmacy or design advice. Work with your pharmacist-in-charge, an architect, engineers, your attorney and the regulators who oversee your pharmacy type.

Know which regulators are involved

A pharmacy buildout answers to more than the city building department. The Texas State Board of Pharmacy sets rules for pharmacy classes, including space, security and equipment expectations, and may inspect before the pharmacy opens. Pharmacies that handle controlled substances also deal with the DEA Diversion Control Division, which has its own security expectations. Inside city limits, building permits run through the Houston Permitting Center.

Ask your pharmacist-in-charge or consultant which rules apply to your pharmacy class before the architect finalizes the layout. It is far easier to change a drawing than a finished wall.

Choosing the right space

Before you sign a lease or buy a building, look at:

Security planning

Security drives much of the pharmacy layout:

CISA's physical security resources offer general guidance, and your security vendor and regulators will define specifics.

Workflow and layout

A pharmacy layout should follow how prescriptions move:

Each step needs counter space, power, data and good lighting. A private counseling area or consult room is common. Will-call storage often grows faster than owners expect, so plan room for it.

Compounding rooms

Compounding pharmacies have the most complex buildouts. Sterile compounding may need a clean-room suite with an anteroom, a buffer room, pressure control, specialized air filtration, smooth cleanable surfaces and sealed ceilings. Hazardous drug compounding may need negative pressure and separate exhaust.

These rooms involve mechanical engineering, certification testing and careful construction sequencing. Talk with your pharmacist-in-charge, a mechanical engineer and a certification firm before the design is set. Our guide to laboratory buildout planning covers many of the same air and finish questions.

Plumbing and sinks

Pharmacies typically need hand sinks and prep sinks in specific locations. Compounding areas may need sinks placed outside the clean rooms. Slab cuts for new drains in an existing suite add time and should be planned early. Our guide to second-generation space explains what can and can't be reused from a prior tenant.

Electrical, data and refrigeration

Confirm service capacity with the building and CenterPoint Energy early.

HVAC and temperature control

Medications have storage temperature limits, and Houston summers are hard on HVAC. Plan for reliable cooling, good humidity control and temperature monitoring in storage areas. Compounding rooms need their own air design. If the suite's rooftop unit is old, review it before opening. Our guide to commercial rooftop HVAC replacement can help.

Accessibility

Customer areas, counters, the counseling room and restrooms must meet accessibility requirements. The 2010 ADA Standards set the federal baseline, and Texas projects may require registration and review through the TDLR Architectural Barriers program. Our guide to ADA items to review in a buildout explains common items.

Finishes

Pharmacy finishes should be durable and easy to clean:

Permits and inspections

Most pharmacy buildouts need building, electrical, plumbing and mechanical permits, plus fire marshal review where required. The Houston Fire Marshal's Office may review the plans. A certificate of occupancy is usually needed before opening. Our guides to the buildout permit process in Houston and the certificate of occupancy for a lease space explain the steps.

Board and federal inspections often happen after construction, so the space must match what was approved on paper.

Lease questions

Our guide to landlord work vs tenant work letters explains how responsibilities are usually divided. Your attorney should review the final lease.

Pharmacy buildout checklist